Projects
Grigoleti-Kobuleti bypass
Length of the construction section - 14.4 km
Donor: the European Investment Bank (EIB)
A 4-lane asphalt concrete road will be constructed
Artificial structures
30 bridge crossings
4 interchanges
Culverts and underpasses
Construction of a new road will fully ensure road capacity for growing traffic flows on an international road of high intensity, also, safe travel and uninterrupted transit traffic. Passing through Grigoleti-Poti and Grigoleti-Kobuleti sections, Samtredia-Grigoleti road will be connected with Kobuleti bypass in two directions from Grigoleti. This will ensure that the traffic flow will move on the high-speed highway passing through Poti as well as directly in the direction of Grigoleti-Kobuleti.
Interactive Map
Progress of the project
23.01.2014
14.02.2014
14.02.2014
14.02.2014
21.11.2014
21.02.2014
21.02.2014