Igoeti-Sveneti section |
Length of the section to be constructed – 25 km.
Donor: The World Bank (WB)
Under the Project, construction works on a 25 km section of four-lane reinforced concrete road at Igoeti-Sveneti section of Tbilisi-Senaki-Leselidze road (km 55-km 80) were carried out. 2 bridges at the river Lekhura and 2 parallel bridge overpasses at the village Igoeti were constructed. 14 underpasses of different sizes and 51 culverts of different sizes were arranged and, moreover, 9 underpasses with the perfect interchange were constructed.
Viaducts:
- 2 parallel viaducts of Igoeti –190 m.
Bridges:
- 2 bridges at the river Lekhura – 81 m.
Underpasses:
- Samtavisi underpass
- Igoeti underpass
- Gamdlistskaro underpass
- Nigoza underpass
- Khurvaleti underpass
- Natsreti, underpass at the Public School in Shavshebi
- Akhalsopeli, Akhalsheni underpass
- Sveneti underpass.
Project implementation dates: 05.03.2008-29.12.2010
Construction works were carried out by the companies: “Ashtromi” Ltd and “New Energy” Ltd.
Sveneti-Ruisi section |
Length of the section to be constructed – 15 km.
Modernization works of the Sveneti-Ruisi section of Tbilisi-Senaki-Leselidze road (km 80-km 95) into the four-lane highway were carried out in 3 lots.
Lot I – km 80-km 84,75 section;
Lot II – km 84,75-km 86,2 section (construction of Liakhvi bridge overpass);
Lot III – km 86,2-km 99 section (construction of Gori tunnels).
Lot I – km 80-km 84.75 section of Tbilisi-Senaki-Leselidze road |
Donor : The World Bank (WB)
Under the Project: construction works of the 4,75 km section four-lane road with reinforced concrete pavement, 19 culverts of different sizes were arranged, also 3 viaducts and 2 bridges were constructed.
Bridges:
- River Tortla with a length of 21 m.
- River Mejuda with a length of 42 m.
Viaducts:
- Gori viaduct with a length of 21 m.
- Viaduct of Gori-Mejvriskhevi direction with a length of 54 m.
- Tskhinvali viaduct with a length of 57 m.
Project implementation dates: 29.07.2009-31.10.2011
Construction works were carried out by the company: “Akkord Industry Construction Investment Corporation” OJSC in Georgia “Akkord Georgia”.
Lot II – km 84,75-km 86,2 section of Tbilisi-Senaki-Leselidze road |
Donor: The World Bank (WB)
Under the Project, four-lane bridge overpass with access roads at the river Liakhvi was constructed. Moreover, 2 culverts and 1 overpass with a length of 877 m at the river Liakhvi were arranged.
Project implementation dates: 01.08.2009-15.05.2013
Construction works were carried out by the company: “Akkord Industry Construction Investment Corporation” OJSC in Georgia “Akkord Georgia”.
Lot III – km 86-km94 section of Tbilisi-Senaki-Leselidze road (construction of tunnels at Gori pass) |
Donor: the World Bank (WB)
Under the Project, construction works of four-lane reinforced concrete road were carried out. 2 tunnels, 1 exit (overpass) and 9 culverts were arranged.
Tunnels:
- Northern tunnel with a length of 783,5 m.
- Southern tunnel with a length of 771,5 m.
Project implementation dates: 29.07.2009-30.06.2013
Construction works are carried out by the company: “TODINI Costruzion Generali SPA”.