According to Roads Department of the Ministry of Regional Development and Infrastructure of Georgia, JSC "Georgian Railway" plans from 08:00 am of May 24, 2021 to 24:00 of May 27 (4 days) to repair odd and even rails existing under a rubber cord cover at guarded level railway crossing at km0 + 300 section of Gomi-Sachkhere-Chiatura-Zestaponi secondary road at Gomi railway station (km 2395 KP3) and site arrangement works on the side of even rails (Sachkhere side), as well as restoration of damaged asphalt-concrete pavement on both sides of the road approaches of the railway crossing.
In order to carry out the mentioned works, it is necessary to temporarily close the carriageway and switch the traffic to a temporary soil road, for which the traffic management technical facilities will be placed.
Relevant staff (wigwaggers) of JSC Georgian Railway will be designated at work zones and at the locations of closure, who will ensure regulation and management of traffic flows during the woks.