Construction of Kobuleti Bypass road (Lot II) is in progress  

Length of the road to be constructed – 18.8 km 

At present earthwork is ongoing (removal of topsoil). Also, reinforced-concrete piles are being constructing at overpass No. 1 (54 piles are constructed). Concurrently production of reinforced-concrete pipes and pre-stressed beams has been commenced at construction base.  

Construction of 18.8 km asphalt-concrete pavement, 16 bridges, 4 overpasses, 2 tunnels and 64 culverts is planned at km12+400-km31-259 section of Kobuleti bypass road.

Width of bridges 17 m, width of the bridge deck 14 m.

Dimension of tunnels – (clearance) 5 m, width of the carriageway – 7,5 m

Works started in June of 2013 and will be completed in 2016.

Contractor: Sinohydro

Project budget: GEL 209,852,079.67

Donor is Asian Development Bank (ADB).


   