05.12.2013
CONSTRUCTION OF E-60 HIGHWAY SAMTREDIAGRIGOLETI
- SECTION Km 0 - Km11,5
ENVIRONMENTAL IMPACT ASSESSMENTI
ntroduction
Promotion of trade with the neighboring countries and development of tourism infrastructures have major importance for the economic development of the country, for which an improved road network is a crucial factor.
The Georgian Government has given the highest priority to improvements of the East - West highway (between Caspian Sea and Black Sea) and North - South (between Russia and Turkey).
|
-
03.12.2013
Detailed Design and Bidding Documents
for Upgrading the Section between Agara Bypass - Gomi Bypass (Zemo Osiauri)
km 114 – km 126 of the E 60 Highway
Resettlement Action Plan
RAP
Section Agara Bypass – Gomi Bypass (Zemo Osiauri)
(km 114 – km 126)
|
-
27.08.13
KAKHETI REGIONAL ROADS IMPROVEMENT PROJECTT
Rehabilitation of Sasadilo-Sioni Road
ENVIRONMENTAL IMPACT ASSESSMENT
Draft Final Report
Road improvements are one of the most successful means of encouraging economic growth and trade in Georgia. At present one of the top national priorities is to establish smooth transport connection between various regions of the country so that the roads network operates throughout the year without traffic delays.
|
-
24.04.13
Environmental Management Plan
for
rehabilitation of secondary road
Ulianivka-Bodbe-Gamarjveba
km 0+000-km 21+347
|
-
24.04.13
Environmental Management Plan
for
rehabilitation of secondary road
Kutaisi-Alpana-Mamisoni Pass
(Oni-Utsera) section
km 116 – km 125
|
-
24.04.13
Environmental Management Plan
for
Kutaisi-Tskhaltubo-Tsageri-Lentekhi-Lasdili
50 Km-63 km
|
-
11.04.13
Environmental Management Plan
for
rehabilitation of secondary road
Tbilisi - Tianeti
km 39 - km 51
Tbilisi, Georgia
|
-
29.03.2013
Final Resettlement Action Plan
RAP
Section Agara Bypass – Gomi Bypass (Zemo Osiauri)
(km 114 – km 126)
|
Eptisa Servicios de Ingenieria, S.L.
|
29 March, 2013
|
|
|
-
27.03.13
Roads Department of the Ministry of Regional Development and Infrastructure of Georgia
Environmental Impact Assessment of works for upgrading E-60 East-West Highway section between Agara– Zemo Osiauri section (km 114 to km 126)
February, 2013
|
-
06.03.2013
Draft Resettlement Action Plan
RAP
Section Agara Bypass – Gomi Bypass (Zemo Osiauri)
(km 114 – km 126)
|
-
04.03.13
Environmental Management Plan
for
rehabilitation of secondary road
Shulaveri-Red bridge road km7-km11
PART 1: GENERAL PROJECT AND SITE INFORMATION
|
-
18.02.2013
Environmental Management Plan
Rehabilitation of the secondary road
Shukruti-Usakhelo-Korbouli
km 5+100 – km 23+500
The proposed project supports the priorities of the Roads Department of the Ministry of Regional Development and Infrastructure (RDMRDI) and of the Bank's assistance strategy for Georgia through
|
-
18.02.2013
Environmental Management Plan
for
rehabilitation of secondary road
Kutaisi – Alpana-Mamisoni Pass
km 77+510–km 82+486
The proposed project supports the priorities of the Roads Department of the Ministry of Regional Development and Infrastructure (RDMRDI) and of the Bank's assistance strategy for Georgia through
|
-
18.02.2013
Environmental Management Plan
for
rehabilitation of secondary road
Rehabilitation DidiDmanisi-Dmanisi-Gomareti-Bediani
road section km 17-km 26
The proposed project supports the priorities of the Roads Department of the Ministry of Regional Development and Infrastructure (RDMRDI) and of the Bank's assistance strategy for Georgia through
|
-
18.02.2013
Environmental Management Plan
for
rehabilitation of secondary road
Chokhatauri - Bakhmaro road
Km 4+000 – km 6+000
The proposed project supports the priorities of the Roads Department of the Ministry of Regional Development and Infrastructure (RDMRDI) and of the Bank's assistance strategy for Georgia through
|
-
06.02.2013
Environmental Impact Assessment of works for upgrading E-60 East-West Highway section between Agara – zemo osiauri section (km 114 to km 126)
Introduction
Due to its geographical position Georgia has gained the status of an important transport corridor connecting Europe and Asia and the development of the transport infrastructure has become a national priority. The Government of Georgia requested the World Bank to support modernization of the East-West Transport Corridor. Two projects for the improvement of the E-60 East-West Highway have already been completed with the assistance from the World Bank and the Third East-West Highway Improvement project is under implementation Future investments will complete improvement of the Highway from Ruisi to the already rehabilitated Rikoti tunnel. A Regional Environmental Assessment (REA) and an Environmental Management Framework (EMF) were developed for the entire corridor Sveneti-Ruisi-Rikoti Tunnel.
|
-
9.01.2013
Environmental Impact Assessment of works for upgrading E-60 East-West Highway section between Agara West – Didi Sative section (km 114 to km 126)
Due to its geographical position Georgia has gained the status of an important transport corridor connecting Europe and Asia and the development of the transport infrastructure has become a national priority. The Government of Georgia requested the World Bank to support modernization of the East-West Transport Corridor. Two projects for the improvement of the E-60 East-West Highway have already been completed with the assistance from the World Bank and the Third East-West Highway Improvement project is under imple-mentation Future investments will complete improvement of the Highway from Ruisi to the already rehabilitated Rikoti tunnel.
|
-
19.11.2012
Environmental Impact Assessment of works for upgrading E-60
East-West Highway section between Ruisi and Agara West (km 95 to km 114)
Introduction
The Georgian Government has embarked on a programme to upgrade the major roads of the country, managed by the Roads Department (RD) of the Ministry of Regional Development and Infrastructure. The initial studies are focused on E-60 East-West Highway (EWH), which is the main route from the neighbouring Azerbaijan and Russia, with connections to Turkey and Armenia.
|
-
12.04.2012
MINISTRY OF REGIONAL DEVELOPMENT AND
INFRASTRUCTURE OF GEORGIA
ROADS DEPARTMENT
Road Corridor Investment Program
Kobuleti Bypass Road, Kobuleti-Batumi Section
and Batumi Bypass Road Design Project
Project Description
The present project is financed by the loan ADB 2560-GEO, Road Corridor Investment Program (Tranche 1) for Preparation of Detailed Design and Preparation of Bidding Documents for Kobuleti Bypass Road, Kobuleti-Batumi Section and Kobuleti Bypass Road.
The project road, bypassing the Kobuleti from East, is entirely located in Kobuleti District and the most part of the road follows the new alignment and will cross mostly the agricultural and household plots.
|
-
09.02.2012
Roads Department of the Ministry of Regional Development and Infrastructure
Land Acquisition and Resettlement Plan
RAP-I
Draft
Section 1 Ruisi - Agara-Agara Bypass (km 0.0 – km 19.0)
EXECUTIVE SUMMARY
1. The Government of Georgia has requested the World Bank’s assistance in upgrading several segments of the East-West highway. The section between Ruisi and Rikoti of approximately 49 km is a two-lane carriageway road, which passes through mountainous and flat terrain. The upcoming investment is intended for upgrading the section from 2-lane to 4-lane highway.
|
|
|