Batumi Bypass Road Construction in active progress
Batumi Bypass Road Construction in active progress
28 May, 2019 09:48:45

The construction of Batumi bypass 13km road section is provided by the Ministry of Regional Development and Infrastructure. First Deputy Minister, Chairman of Roads Department Mr. Irakli Karseladze and deputy chairman – Levan Kupatashvili inspected ongoing works.

At this stage, earthworks, the arrangement of culverts and underpasses and the construction works for bridges and tunnels are in progress.

During the project,2-lane asphalt concrete road, 19 bridge crossing,4 interchanges, 5tunnels and 57 culverts will be constructed.The new bypass way will pass through:Maxinjauri,Gantiadi,Kapreshumi,Salibauri,Peria,Makhvilauri,Khelvachauri.

Nowadays, existing road passes through the tourist and residential zone, which complicates the flow of international transit traffic. As a result of project implementation, Batumi bypass road (together with Kobuleti bypass road) will fully relieve traffic in the Adjara resort zone, which promotes an increase of transit turnover. Ecological condition will significantly change for the better.

The project is financed under the loan agreements signed with the Asian Development Bank (ADB) and the Asian Infrastructure Investment Bank (AIIB). The cost of the agreement amounts to GEL 329 630 734. Period of construction works is 2017-2010.