Roads Department of the Ministry of Regional Development and Infrastructure of Georgia, is implemented rehabilitation works of 6.4 km Tsitsamuri-Saguramo-Ckhvarichamia road.
Rehabilitation section starts from Village Navdaraantkari and ends at Village Buriani.
Tsitsamuri-Saguramo-Ckhvarichamia road enables villages located along the road to connect with the municipal center , Capital Tbilisi and central highway -with the shortest route.
Under the project technical parameters of the road will improve, rehabilitation of structures, arrangement of road pavement and equip the road with modern elements for road safety, which will significantly contribute surrounding villages economical, social and touristic development.
At this stage, asphalt-concrete pavement works are ongoing.
Rehabilitation works inspected Deputy Chairman of Roads Department Irakli Khergiani.
Project is financed from the state budget and its cost is GEL 2 934 300. Rehabilitation will be completed in autumn 2016.