Construction of the Agara-Zemo osiauri road activated with the weather improving
Construction of the Agara-Zemo osiauri road activated with the weather improving
18 February, 2016 00:00:00

Roads Department of the Ministry of Regional Development and Infrastructure of Georgia provides  updated photo materials reflecting construction progress of Agara-Zemo Osiauri section in the category of weekly pictures gallery,which was suspended due to heavy snows.

Construction of the Agara-Zemo osiauri road activated with the weather improving. Mentioned section of Agara-Zemo Osiauri is a part of main transit route of the country, At 12 km section construction project it is envisaged to construct 4-lane highway with cement-concrete pavement, 8 parallel bridges,  interchanges, footbridges, underpasses and reinforced concrete culverts. Also, along section shore protection structure works.

Currently, pavement has been constructed along 3 km in 4- lane highway. At this stage, construction of road base and structures are underway on respective section.

According to the project construction period for 12 km long section is 27 month . Construction of 7 km section will be completed by the end of the current year. After that, traffic shall be shifted to a new four-lane cement-concrete road.

Georgian Company Black Sea Group and Kuwait Company Corpi Construction Enterprises W.L.L implement civil works. Project is financed by the World Bank. Project value is more than GEL 105,7 mln