​Detailed information about Kutaisi bypass road
​Detailed information about Kutaisi bypass road
19 November, 2014 00:00:00
Today a new 32 km section of E60 East-West Highway – Kutaisi Bypass Road was opened. This is the largest section of the highway that has been opened up to date. 
In order to inform our citizens about the details of the launch, progress and completion stages of this large-scale project, we believe a number of important points should be clarified.
Activities carried out in 2012 entailed preparatory and land works, while in 2013-2014 main construction works were implemented, including building of artificial edifices (transportation knots, viaducts, bridges, culverts) and arrangement of concrete pavement. Specifically: in 2011 designing of Zestaponi-Kutaisi-Samtredia section constructions of East-West Highway was launched. Construction works on the first section started on December 25, 2011 and by 2012, cost of conducted works amounted to 16 844 919.47 GEL. On the second section works started on 18 July, 2012 and by the end of the year costs equaled 7 444 732.56 GEL.
In 2013, road construction implementation on two sections (Kutaisi Bypass Road, Kutaisi Bypass-Samtredia Section) of Zestaponi-Kutaisi-Samtrediacost 79 944 743.93 GEL and in 2014, 7 438 080.62 GEL. The abovementioned data affirms that major construction works of Zestaponi-Kutaisi-Samtredia road segment of East-West Highway were carried out in 2013-2014. 
Today a new 32 km section of E60 East-West Highway – Kutaisi Bypass Road was opened. This is the largest section of the highway that has been opened up to date. In order to inform our citizens about the details of the launch, progress and completion stages of this large-scale project, we believe a number of important points should be clarified.Activities carried out in 2012 entailed preparatory and land works, while in 2013-2014 main construction works were implemented, including building of artificial edifices (transportation knots, viaducts, bridges, culverts) and arrangement of concrete pavement. Specifically: in 2011 designing of Zestaponi-Kutaisi-Samtredia section constructions of East-West Highway was launched. Construction works on the first section started on December 25, 2011 and by 2012, cost of conducted works amounted to 16 844 919.47 GEL. On the second section works started on 18 July, 2012 and by the end of the year costs equaled 7 444 732.56 GEL.In 2013, road construction implementation on two sections (Kutaisi Bypass Road, Kutaisi Bypass-Samtredia Section) of Zestaponi-Kutaisi-Samtrediacost 79 944 743.93 GEL and in 2014, 7 438 080.62 GEL. The abovementioned data affirms that major construction works of Zestaponi-Kutaisi-Samtredia road segment of East-West Highway were carried out in 2013-2014. 