Rehabilititon of Gomi-Sachkhere-Chiatura road is underway
Rehabilititon of Gomi-Sachkhere-Chiatura road is underway
29 July, 2014 00:00:00

The works for rehabilitation of secondary Gomi-Sachkhere-Chiatura road in Imereti region is actively progressing. Rehabilitation works are being implemented at two sections of mentioned road (km25-km34; km36; km43-km45), which in total is 13.8 km.

Gomi-Sachkhere-Chiatura road is the shortest route to connect with the capital and rest eastern Georgia for more than 10 villages and about 15 000 residents. Mentioned section, if Rikoti pass road is closed, serves as an alternative road connecting east and west Georgia.

The works for rehabilitation of both sections of Gomi-Sachkhere-Chiatura road (km25-km34; km36; km43-km45) is performed by “Fin-estate” Ltd. and its total cost amounts to GEL 8,439K. About 200 people have been employed for mentioned works, out of which 60% are local residents. Rehabilitation of mentioned road will be completed by the end of the current year.

At this stage, the preparatory works have already been completed and the works related to cut and filling of damaged pavement, construction of sub-base layer, recycling, strengthening of roadbed, arrangement of culvert head and delivery of sand-gravel material are ongoing.   The project envisages construction of asphalt pavement, cleaning and repair of the existing culverts, construction of new culverts and structures, installation of gabion retaining walls, repair works at bridges and enclosed bus stops, installation of road signs and indicators, horizontal and vertical marking of the pavement.

Rehabilitation of the road will foster increase of carrying capacity of the road, comfortable and safe travel between the settled areas and improvement of social conditions of population.